|
1
|
|
|
2
|
|
|
3
|
|
|
4
|
|
|
5
|
|
|
6
|
|
|
7
|
|
|
8
|
|
|
9
|
|
|
10
|
|
|
11
|
|
|
12
|
|
|
13
|
|
|
14
|
|
|
15
|
|
|
16
|
|
|
17
|
|
|
18
|
- Operational savings for leachate transportation and treatment
- Increased Density – 10 to 20 % = More capacity
- Quicker gas capture drastically improves economics of landfill gas to
energy
- Potential lower long-term liability
|
|
19
|
- The existing base model will be a comparative model, using the slightly
modified landfill capacity that we have calculated
- No changes are to be made to the current base model configuration other
than reduce the Base Case clay layer in the secondary liner to 2 feet to
correspond to the Model 1 & 2 scenarios.
- Minor changes will be made to the base model data to reflect our
interpretation of the mapping and make it more comparable with our
alternatives calculations.
- The current base model data will be included in the revised economic
model.
- A cost of $0.20 per gallon to treat leachate will be used based upon the
average costs of 1996 and 1997, when leachate strength was most
representative of newer waste.
- A 25% contingency will be used for construction costs and a 15%
contingency will be used for operating costs. These will be accounted at the end of
the calculations rather than by line item.
|
|
20
|
- The following alternatives will be used in Model 1:
- Final grades for a 10-foot perimeter wall will be used.
- Slopes consistent with base model.
- No change in site geometry from the base model.
- Biostabilization assumes 15% by volume settlement of the in place waste
due to the accelerated decomposition of the putrescible waste.
- Base liner as described above.
- Final Cover as described above.
- Deep Liner with Groundwater Control System as described above.
- Alternative daily will be used in both Models 1 and 2 at a rate of 10%
of total volume.
- No waste processing.
|
|
21
|
- The following alternatives will be used in Model 2:
- Final grades for a 20-foot perimeter wall will used for Model 2
- Final grades for the slope-optimized alternative will be extended at a
3H:1V slope 10 feet higher than the added effects of the walls, i.e. 30
feet higher than the Base Model and 20 feet higher than Model 1.
- No change in site geometry from the base model
- Biostabilization assumes a 15% by volume settlement of the waste in
place due to the accelerated decomposition of the putrescible waste.
- Base liner as described above
- Final Cover as described above
- Deep Liner with Groundwater Control System as described above
- Alternative daily will be used in both Models 1 and 2 at a rate of 10%
of total volume.
- No waste processing.
|