Notes
Slide Show
Outline
1
 
2
 
3
 
4
 
5
 
6
 
7
 
8
 
9
 
10
 
11
 
12
 
13
Operations Management
14
 
15
 
16
 
17
 
18
Benefits of a Bioreactor Landfill
  • Operational savings for leachate transportation and treatment
  • Increased Density – 10 to 20 % = More capacity
  • Quicker gas capture drastically improves economics of landfill gas to energy
  • Potential lower long-term liability
19
Base Model
  • The existing base model will be a comparative model, using the slightly modified landfill capacity that we have calculated


  • No changes are to be made to the current base model configuration other than reduce the Base Case clay layer in the secondary liner to 2 feet to correspond to the Model 1 & 2 scenarios.
  • Minor changes will be made to the base model data to reflect our interpretation of the mapping and make it more comparable with our alternatives calculations.
  • The current base model data will be included in the revised economic model.
  • A cost of $0.20 per gallon to treat leachate will be used based upon the average costs of 1996 and 1997, when leachate strength was most representative of newer waste.
  • A 25% contingency will be used for construction costs and a 15% contingency will be used for operating costs.  These will be accounted at the end of the calculations rather than by line item.


20
Model 1 – Intermediate Build-Out
  • The following alternatives will be used in Model 1:


  • Final grades for a 10-foot perimeter wall will be used.
  • Slopes consistent with base model.
  • No change in site geometry from the base model.
  • Biostabilization assumes 15% by volume settlement of the in place waste due to the accelerated decomposition of the putrescible waste.
  • Base liner as described above.
  • Final Cover as described above.
  • Deep Liner with Groundwater Control System as described above.
  • Alternative daily will be used in both Models 1 and 2 at a rate of 10% of total volume.
  • No waste processing.


21
Model 2 – Maximum Build-Out
  • The following alternatives will be used in Model 2:


  • Final grades for a 20-foot perimeter wall will used for Model 2
  • Final grades for the slope-optimized alternative will be extended at a 3H:1V slope 10 feet higher than the added effects of the walls, i.e. 30 feet higher than the Base Model and 20 feet higher than Model 1.
  • No change in site geometry from the base model
  • Biostabilization assumes a 15% by volume settlement of the waste in place due to the accelerated decomposition of the putrescible waste.
  • Base liner as described above
  • Final Cover as described above
  • Deep Liner with Groundwater Control System as described above
  • Alternative daily will be used in both Models 1 and 2 at a rate of 10% of total volume.
  • No waste processing.